Groton Parks & Recreation: Park Improvement Projects

Park infrastructure replacement and new construction are investments in the community. Many of the projects are based on needs identified in the 2020 Community Needs Survey and align with our Strategic Plan to “Plan, design, build and maintain new facilities that are accessible to individuals and community groups of all physical capabilities, skill levels, age groups, income levels, cultural groups and activity interests.”  Each Groton Park & Recreation parks improvement project is listed below based on what stage of the process it is in. Click on any of the lists of stages below to view details of each project.
  • Completed
  • Identified
  • In Progress
  • Initiated
  • Scheduled
D
  • Completed

Deerfield Basketball Court

Description
Basketball Court was removed due to extensive cracking. Site was regraded and new court was laid down. Court will be lined and painted in the Spring.

Cost
$12,000 paving
$16,000 lining and painting

Start - End
Fall 2020 - Summer 2021

Contractor
Demolition, site prep and paving was done in-house.
Lining and painting Hinding Tennis LLC.

Read More
G
  • In Progress

Groton Community Center Field Restoration

Description
Complete design and regrade athletic field to improve drainage and make conditions safer by removing uneven surface.  Install irrigation system to help maintain healthy and safe turf conditions.

Cost
$129,750
- Maxum Irrigation $52,250
- Whittles Farm (topsoil) $64,000
Start - End
Fall 2022 - fields ready for play in Fall 2023

Contractor
Public Works doing field work and contractor providing irrigation.
Read More
M
  • Completed

Millwood Creek Disc Golf

Description    
The project includes replacing disc golf baskets and installing tee boxes. Directional signage and course map added.  

Cost            
$20,000  using State LoCIP funds

Start - End

Fall 2020 - Fall 2022

Contractor    
Clearing for re-located holes – Park & Forestry staff.
Installation of baskets and tee boxes by volunteers
Sign vendor: FastSigns
Read More
P
  • In Progress

Poquonnock Plains Park Walking Path Widening

Description:
Park staff is widening the walking path around the athletic fields. Widening the path will allow staff to be better able to maintain the path. 
Projected Cost:
$12.000
Start - End:
Winter 2023 - Work will continue into the Spring and resume in the Fall.
Read More
T
  • Completed

Tanglewood Park Basketball Court

Description
Basketball court was removed, site was regraded, new court was laid down and a new row of screening shrubs was added. Court will be lined and painted in Spring 2021.

Cost
$12,000 paving
$16,000 lining and painting

Start - End
Fall 2020 - Summer 2021                                       

Contractor
Demolition, site prep and paving  was completed in-house.
Lining and painting Hinding Tennis LLC.
Read More